Riccarton Road Wastewater Upgrade

Client

Fulton Hogan


Start Date

June 15th 2019


Location

Riccarton, Christchurch


Value

$3,050,000


Project

Civil / Drainage Construction


MORE DETAILS
Civil Drainage Riccarton Road Wastewater Upgrade 1
Pic 1. Excavating 300mm for sheetpile installation.
Civil Drainage Riccarton Road Wastewater Upgrade 2
Pic 2. Installation of sheetpile.
Civil Drainage Riccarton Road Wastewater Upgrade 3
Pic 3. Trench excavation.
Civil Drainage Riccarton Road Wastewater Upgrade 4
Pic 4. Raft Installation.
Civil Drainage Riccarton Road Wastewater Upgrade 5
Pic 5. Base prep for pipe installation.
Civil Drainage Riccarton Road Wastewater Upgrade 6
Pic 6. Installation of DN500 pipe.

Christchurch City Council Engaged Fulton Hogan to undertake a number of projects to upgrade services and roading along Riccarton Road including a major upgrade of the wastewater network. Riccarton Road is a significant through route in Christchurch, as such a key objective was to ensure minimal disruption to traffic and stakeholders.

Martin Civil Construction’s role in the work was to increase the capacity of the wastewater network to reduce wet weather surcharges and provide new, resilient wastewater infrastructure assets between Matipo and Harakeke Street.

 

Martin Civil Construction, subcontracted to Fulton Hogan undertook

    • Installation of DN500 PVC-U SN16 wastewater main pipes in 3-4m trench
    • Installation of DN375 PVC-U SN16 wastewater main pipes in 2-3m and 3-4m trench
    • Installation of sanitary sewer wastewater collectors (225 PVC SN 16)
    • Installation of 1200mm square and circular manholes, 4m and 6m sheet piles and trench shields
    • Installation of a 400mm and 900mm Raft under pipes and Manholes
    • Installation of sanitary sewer laterals
    • Support of services crossing the trench
    • CCTV, Ovality and pressure testing of DN 500 and DN 375 pipelines, including hydrostatic testing of the DN500 line
    • Removal of existing pipes and relay with new DN150 PVC-U SN16 and connect into existing lines and into new manholes
    • Grouting of existing redundant earthenware pipelines

 

Key challenges

    • Trench depth breached water table requiring 24 hour dewatering of trenches and regular sediment/contaminant testing alongside control measures
    • Limited work spaces in some areas requiring careful project planning to ensure most efficient use of space
    • Limited access to site at some areas for side street connections

Reference Letter

Privacy Settings
We use cookies to enhance your experience while using our website. If you are using our Services via a browser you can restrict, block or remove cookies through your web browser settings. We also use content and scripts from third parties that may use tracking technologies. You can selectively provide your consent below to allow such third party embeds. For complete information about the cookies we use, data we collect and how we process them, please check our Privacy Policy
Youtube
Consent to display content from - Youtube
Vimeo
Consent to display content from - Vimeo
Google Maps
Consent to display content from - Google
Spotify
Consent to display content from - Spotify
Sound Cloud
Consent to display content from - Sound